Influence of cost contingency management on project estimates at completion

The Earned Value Management (EVM) methodology provides an index-based Estimate at Completion (EAC) formula to forecast the final cost of an ongoing project. However, neither the EVM methodology nor the literature in cost forecasting considers the occurrence of risks and how the cost contingency rese...

Full description

Saved in:
Bibliographic Details
Published in:International journal of construction management Vol. 24; no. 9; pp. 935 - 945
Main Authors: De Marco, Alberto, Narbaev, Timur, Ottaviani, Filippo Maria, Vanhoucke, Mario
Format: Journal Article
Language:English
Published: Taylor & Francis 03-07-2024
Subjects:
Online Access:Get full text
Tags: Add Tag
No Tags, Be the first to tag this record!
Description
Summary:The Earned Value Management (EVM) methodology provides an index-based Estimate at Completion (EAC) formula to forecast the final cost of an ongoing project. However, neither the EVM methodology nor the literature in cost forecasting considers the occurrence of risks and how the cost contingency reserve (CC) is used to mitigate them. This study proposes a risk-adjusted cost EAC methodology based on nonlinear regression that captures the CC spending profile and exploits it to improve the EAC forecasting performance. The CC spending profile reflects the preventive, neutral, or reactive risk management strategy (RMS) adopted, which dictates how the CC reserve is depleted throughout the project execution. The framework was tested on a dataset comprising 79 constructions and engineering projects to evaluate its performance across the projects' early, mid, and late stages. Results show that the proposed methodology provides timely forecasts-mean absolute percentage error (MAPE) improves as the project progresses-and that a proactive RMS is the most reliable one in all stages, with MAPE values of 14.57%, 12.28%, and 11.42%, respectively.
ISSN:1562-3599
2331-2327
DOI:10.1080/15623599.2023.2239487