Forensic Analysis of the Disputes Typology of the NSW Construction Industry Using PLS-SEM and Prospective Trend Analysis

Project claim management is the central pillar of the overlapping areas of contract administration, contract law and building regulations. Delays caused by inefficiency of the procedures designed to avoid disputes emerge at the pre-project phase and continue during construction. The quantum of resea...

Full description

Saved in:
Bibliographic Details
Published in:Buildings (Basel) Vol. 12; no. 10; p. 1571
Main Authors: Rahnamayiezekavat, Payam, Sorooshnia, Ehsan, Rashidi, Maria, Faraji, Amir, Mostafa, Sherif, Moon, Sungkon
Format: Journal Article
Language:English
Published: Basel MDPI AG 01-10-2022
Subjects:
Online Access:Get full text
Tags: Add Tag
No Tags, Be the first to tag this record!
Abstract Project claim management is the central pillar of the overlapping areas of contract administration, contract law and building regulations. Delays caused by inefficiency of the procedures designed to avoid disputes emerge at the pre-project phase and continue during construction. The quantum of research addressing this issue is not immediately transferrable between jurisdictions, mainly due to local specificity of construction practices, contract and construction laws, as well as clients’ preferences. The primary aim of this study is to identify the underlying causes of disputes that have arisen in the NSW construction industry in the past two decades and to analyze the inter-relationships between the causes. To achieve this purpose, PLS-SEM quantitative models were utilized to study different factors influencing disputes. Through a detailed quantitative analysis of 230 cases, based on dispute frequencies, causes and effect analysis and the resultant loop cause diagrams, the dispute triggers, types, and root causes have been analyzed as the basis for developing a model to predict the future likelihood of disputes. Finally, 13 causes of disputes have been recognized as the main causal factors in the construction projects in NSW. This study also has shown that payment and reimbursement-related disputes are the most frequent in NSW construction, except for the last two years.
AbstractList Project claim management is the central pillar of the overlapping areas of contract administration, contract law and building regulations. Delays caused by inefficiency of the procedures designed to avoid disputes emerge at the pre-project phase and continue during construction. The quantum of research addressing this issue is not immediately transferrable between jurisdictions, mainly due to local specificity of construction practices, contract and construction laws, as well as clients’ preferences. The primary aim of this study is to identify the underlying causes of disputes that have arisen in the NSW construction industry in the past two decades and to analyze the inter-relationships between the causes. To achieve this purpose, PLS-SEM quantitative models were utilized to study different factors influencing disputes. Through a detailed quantitative analysis of 230 cases, based on dispute frequencies, causes and effect analysis and the resultant loop cause diagrams, the dispute triggers, types, and root causes have been analyzed as the basis for developing a model to predict the future likelihood of disputes. Finally, 13 causes of disputes have been recognized as the main causal factors in the construction projects in NSW. This study also has shown that payment and reimbursement-related disputes are the most frequent in NSW construction, except for the last two years.
Author Moon, Sungkon
Sorooshnia, Ehsan
Rashidi, Maria
Faraji, Amir
Rahnamayiezekavat, Payam
Mostafa, Sherif
Author_xml – sequence: 1
  givenname: Payam
  surname: Rahnamayiezekavat
  fullname: Rahnamayiezekavat, Payam
– sequence: 2
  givenname: Ehsan
  surname: Sorooshnia
  fullname: Sorooshnia, Ehsan
– sequence: 3
  givenname: Maria
  orcidid: 0000-0003-2847-3806
  surname: Rashidi
  fullname: Rashidi, Maria
– sequence: 4
  givenname: Amir
  surname: Faraji
  fullname: Faraji, Amir
– sequence: 5
  givenname: Sherif
  orcidid: 0000-0002-5708-3770
  surname: Mostafa
  fullname: Mostafa, Sherif
– sequence: 6
  givenname: Sungkon
  surname: Moon
  fullname: Moon, Sungkon
BookMark eNplUdlqGzEUFcGBpEk-IG-CPE-r1Zp5DK7dGNwmYIc8Co0WR2YqTaWZkvn7qnVqChUXdJfDOXf5AGYhBgvALUYfKW3Qp3b0nfFhnzHBCHOBz8AlQYJXnKJm9o9_AW5yPqDyak4IZ5fgbRWTDdlreB9UN2WfYXRweLXws8_9ONgMd1Mfu7if_ha-bV_gIoY8pFEPPga4DmYs0QSfc2kCPm221Xb5Fapg4FOKubcF9tPCXREyJ5lrcO5Ul-3N-38FnlfL3eKh2jx-WS_uN5WmNRkqbbTlBJvaKM5rq4Vu5wwb6hpLW8eMQy3TAinumEKWz0ltmSFIz0vGGkXoFVgfeU1UB9kn_12lSUbl5Z9ETHup0uB1ZyVDlIlaU61Yw4RoGleW2zZFniAllCtcd0euPsUfo82DPMQxlYGyJILUjBVrCgofUboMn5N1J1WM5O97yf_uRX8BAZ2NdA
CitedBy_id crossref_primary_10_3233_JIFS_221334
crossref_primary_10_3233_JIFS_221410
Cites_doi 10.1061/(ASCE)0733-9364(2001)127:3(223)
10.5130/AJCEB.v16i1.4600
10.1061/(ASCE)LA.1943-4170.0000491
10.2753/MTP1069-6679190407
10.3390/su10051415
10.1061/(ASCE)0733-9364(1995)121:4(355)
10.1016/j.jfbs.2014.01.002
10.1108/eb021042
10.1016/j.proeng.2011.11.156
10.1108/ECAM-03-2018-0109
10.1111/j.1467-6486.1992.tb00668.x
10.3846/jcem.2021.14900
10.1061/(ASCE)LA.1943-4170.0000525
10.1016/j.ijproman.2005.11.003
10.1007/978-3-030-15009-9
10.1007/978-3-319-04429-3
10.1061/(ASCE)CO.1943-7862.0002208
10.1111/j.1467-6486.1992.tb00664.x
10.1016/j.ijproman.2006.11.007
10.1016/j.ijproman.2007.05.002
10.1007/s11747-011-0261-6
10.1016/j.lrp.2014.02.003
10.3389/fpsyg.2012.00111
10.1007/978-3-319-71691-6_6
10.1108/17561451211211732
10.1016/S0965-9978(03)00105-4
10.1007/978-3-319-04429-3_2
10.1080/014461997372719
10.1061/(ASCE)0742-597X(2004)20:3(88)
10.2753/MTP1069-6679190202
10.1061/(ASCE)CF.1943-5509.0000054
10.1007/978-90-481-9097-3_17
10.4337/9781781001042.00023
10.1007/978-3-030-80256-1_4
10.1061/(ASCE)LA.1943-4170.0000498
10.1007/978-1-84882-809-4
10.1016/j.buildenv.2005.09.004
10.1016/j.lrp.2014.02.007
10.1061/(ASCE)LA.1943-4170.0000508
10.1016/j.ijproman.2005.11.010
10.1108/00251740510593576
10.1061/(ASCE)LA.1943-4170.0000519
10.1007/978-3-540-32827-8_3
10.4324/9781410604385
10.1007/978-3-319-71691-6
10.1007/s11747-011-0300-3
10.1109/ACCESS.2020.2976109
10.1108/09699981011056592
10.1007/s10506-021-09281-9
10.1061/(ASCE)0733-9364(2002)128:1(18)
10.1007/978-3-540-32827-8_15
10.1155/2018/3696457
10.1061/(ASCE)LA.1943-4170.0000520
10.1007/978-3-030-80519-7
10.1108/14714170110814550
10.1061/(ASCE)CO.1943-7862.0000532
10.1007/978-1-349-21005-3_20
10.1061/9780784402764
10.1108/S1474-7979(2009)0000020014
ContentType Journal Article
Copyright 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/). Notwithstanding the ProQuest Terms and Conditions, you may use this content in accordance with the terms of the License.
Copyright_xml – notice: 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/). Notwithstanding the ProQuest Terms and Conditions, you may use this content in accordance with the terms of the License.
DBID AAYXX
CITATION
8FD
8FE
8FG
ABJCF
ABUWG
AFKRA
ATCPS
AZQEC
BENPR
BGLVJ
BHPHI
CCPQU
DWQXO
FR3
GNUQQ
HCIFZ
KR7
L.-
L6V
M7S
PATMY
PIMPY
PQEST
PQQKQ
PQUKI
PTHSS
PYCSY
DOA
DOI 10.3390/buildings12101571
DatabaseName CrossRef
Technology Research Database
ProQuest SciTech Collection
ProQuest Technology Collection
Materials Science & Engineering Collection
ProQuest Central (Alumni)
ProQuest Central UK/Ireland
Agricultural & Environmental Science Collection
ProQuest Central Essentials
ProQuest Central
Technology Collection
Natural Science Collection
ProQuest One Community College
ProQuest Central
Engineering Research Database
ProQuest Central Student
SciTech Premium Collection
Civil Engineering Abstracts
ABI/INFORM Professional Advanced
ProQuest Engineering Collection
Engineering Database
Environmental Science Database
Publicly Available Content Database
ProQuest One Academic Eastern Edition (DO NOT USE)
ProQuest One Academic
ProQuest One Academic UKI Edition
Engineering Collection
Environmental Science Collection
Directory of Open Access Journals
DatabaseTitle CrossRef
Publicly Available Content Database
ProQuest Central Student
Technology Collection
Technology Research Database
ProQuest Central Essentials
ProQuest Central (Alumni Edition)
SciTech Premium Collection
ProQuest One Community College
ProQuest Central
ABI/INFORM Professional Advanced
ProQuest Engineering Collection
Natural Science Collection
ProQuest Central Korea
Agricultural & Environmental Science Collection
Engineering Collection
Civil Engineering Abstracts
Engineering Database
ProQuest One Academic Eastern Edition
ProQuest Technology Collection
ProQuest SciTech Collection
Environmental Science Collection
ProQuest One Academic UKI Edition
Materials Science & Engineering Collection
Environmental Science Database
Engineering Research Database
ProQuest One Academic
DatabaseTitleList
CrossRef
Publicly Available Content Database
Database_xml – sequence: 1
  dbid: DOA
  name: Directory of Open Access Journals
  url: http://www.doaj.org/
  sourceTypes: Open Website
DeliveryMethod fulltext_linktorsrc
Discipline Engineering
EISSN 2075-5309
ExternalDocumentID oai_doaj_org_article_403478c3ca4947799f390b952120a7af
10_3390_buildings12101571
GeographicLocations Australia
GeographicLocations_xml – name: Australia
GroupedDBID .4S
2XV
5VS
7XC
8FE
8FG
8FH
AAFWJ
AAYXX
ABJCF
ADBBV
AFKRA
AFPKN
ALMA_UNASSIGNED_HOLDINGS
ARCSS
ATCPS
BCNDV
BENPR
BGLVJ
BHPHI
CCPQU
CITATION
GROUPED_DOAJ
HCIFZ
IAO
ITC
KQ8
L6V
M7S
MODMG
M~E
OK1
PATMY
PIMPY
PROAC
PTHSS
PYCSY
RIG
TUS
8FD
ABUWG
AZQEC
DWQXO
FR3
GNUQQ
KR7
L.-
PQEST
PQQKQ
PQUKI
ID FETCH-LOGICAL-c382t-cdce521d8da558ec7cb641d3f9e3bf4df0b4c70a5f4a0e5628e4d20c6a5feda23
IEDL.DBID DOA
ISSN 2075-5309
IngestDate Tue Oct 22 15:11:21 EDT 2024
Mon Nov 04 15:17:50 EST 2024
Wed Aug 07 14:13:24 EDT 2024
IsDoiOpenAccess true
IsOpenAccess true
IsPeerReviewed true
IsScholarly true
Issue 10
Language English
LinkModel DirectLink
MergedId FETCHMERGED-LOGICAL-c382t-cdce521d8da558ec7cb641d3f9e3bf4df0b4c70a5f4a0e5628e4d20c6a5feda23
ORCID 0000-0002-5708-3770
0000-0003-2847-3806
OpenAccessLink https://doaj.org/article/403478c3ca4947799f390b952120a7af
PQID 2728448449
PQPubID 2032422
ParticipantIDs doaj_primary_oai_doaj_org_article_403478c3ca4947799f390b952120a7af
proquest_journals_2728448449
crossref_primary_10_3390_buildings12101571
PublicationCentury 2000
PublicationDate 2022-10-01
PublicationDateYYYYMMDD 2022-10-01
PublicationDate_xml – month: 10
  year: 2022
  text: 2022-10-01
  day: 01
PublicationDecade 2020
PublicationPlace Basel
PublicationPlace_xml – name: Basel
PublicationTitle Buildings (Basel)
PublicationYear 2022
Publisher MDPI AG
Publisher_xml – name: MDPI AG
References ref_50
Chan (ref_46) 2021; 13
Ravanshadnia (ref_17) 2021; 29
Faraji (ref_15) 2021; 13
Naji (ref_2) 2020; 8
ref_58
ref_57
ref_56
Hair (ref_73) 2011; 19
ref_53
ref_52
Fitriyanti (ref_11) 2022; 14
ref_51
Friedman (ref_78) 1991; 19
ref_19
Cheung (ref_23) 2001; 1
Mitropoulos (ref_48) 2001; 127
Si (ref_65) 2018; 2018
Asadi (ref_13) 2022; 14
Tayeh (ref_10) 2022; 14
Sarstedt (ref_71) 2014; 47
ref_61
ref_60
Ling (ref_31) 2006; 24
Sambasivan (ref_28) 2007; 25
Ilter (ref_20) 2012; 4
ref_69
ref_24
ref_67
Nabi (ref_14) 2022; 148
ref_66
ref_21
ref_64
ref_63
ref_62
ref_26
Love (ref_5) 2010; 17
Diekmann (ref_18) 1995; 121
Illankoon (ref_44) 2019; 22
Tanriverdi (ref_9) 2021; 27
Jaffar (ref_22) 2011; 20
ref_72
Cheung (ref_4) 2004; 20
Chan (ref_39) 2005; 43
Fenn (ref_33) 1997; 15
Selya (ref_75) 2012; 3
ref_36
ref_35
ref_34
ref_76
Chua (ref_25) 2003; 34
Love (ref_40) 2009; 23
Assaf (ref_29) 2006; 24
ref_38
Diamantopoulos (ref_68) 2012; 40
ref_37
Waly (ref_12) 2022; 14
Rigdon (ref_74) 2014; 47
Love (ref_6) 2002; 128
Cossette (ref_55) 1992; 29
ref_47
Ringle (ref_70) 2011; 19
ref_45
ref_42
ref_41
Hair (ref_59) 2012; 40
ref_1
Iyer (ref_43) 2008; 26
Eden (ref_54) 1992; 29
ref_3
Cheung (ref_77) 2013; 139
ref_49
Kumaraswamy (ref_16) 1997; 4
Cheung (ref_27) 2007; 42
ref_8
Livesey (ref_30) 2016; 16
Cheung (ref_32) 2019; 26
ref_7
References_xml – ident: ref_49
– volume: 127
  start-page: 223
  year: 2001
  ident: ref_48
  article-title: Model for understanding, preventing, and resolving project disputes
  publication-title: J. Constr. Eng. Manag.
  doi: 10.1061/(ASCE)0733-9364(2001)127:3(223)
  contributor:
    fullname: Mitropoulos
– ident: ref_26
– ident: ref_51
– volume: 16
  start-page: 90
  year: 2016
  ident: ref_30
  article-title: Insights of project managers into the problems in project management
  publication-title: Constr. Econ. Build.
  doi: 10.5130/AJCEB.v16i1.4600
  contributor:
    fullname: Livesey
– volume: 13
  start-page: 04521026
  year: 2021
  ident: ref_15
  article-title: Multihybrid Dispute Resolution Framework for Projects of Downstream Sector of Petroleum Industry
  publication-title: J. Leg. Aff. Disput. Resolut. Eng. Constr.
  doi: 10.1061/(ASCE)LA.1943-4170.0000491
  contributor:
    fullname: Faraji
– volume: 19
  start-page: 459
  year: 2011
  ident: ref_70
  article-title: Customer Satisfaction with Commercial Airlines: The Role of Perceived Safety and Purpose of Travel
  publication-title: J. Mark. Theory Pr.
  doi: 10.2753/MTP1069-6679190407
  contributor:
    fullname: Ringle
– ident: ref_58
  doi: 10.3390/su10051415
– volume: 121
  start-page: 355
  year: 1995
  ident: ref_18
  article-title: Are Contract Disputes Predictable?
  publication-title: J. Constr. Eng. Manag.
  doi: 10.1061/(ASCE)0733-9364(1995)121:4(355)
  contributor:
    fullname: Diekmann
– ident: ref_63
  doi: 10.1016/j.jfbs.2014.01.002
– volume: 4
  start-page: 95
  year: 1997
  ident: ref_16
  article-title: Conflicts, claims and disputes in construction
  publication-title: Eng. Constr. Archit. Manag.
  doi: 10.1108/eb021042
  contributor:
    fullname: Kumaraswamy
– volume: 20
  start-page: 193
  year: 2011
  ident: ref_22
  article-title: Factors of Conflict in Construction Industry: A Literature Review
  publication-title: Procedia Eng.
  doi: 10.1016/j.proeng.2011.11.156
  contributor:
    fullname: Jaffar
– volume: 26
  start-page: 321
  year: 2019
  ident: ref_32
  article-title: Biases in construction project dispute resolution
  publication-title: Eng. Constr. Archit. Manag.
  doi: 10.1108/ECAM-03-2018-0109
  contributor:
    fullname: Cheung
– volume: 29
  start-page: 325
  year: 1992
  ident: ref_55
  article-title: Mapping of an idiosyncratic schema
  publication-title: J. Manag. Stud.
  doi: 10.1111/j.1467-6486.1992.tb00668.x
  contributor:
    fullname: Cossette
– volume: 27
  start-page: 288
  year: 2021
  ident: ref_9
  article-title: Causal mapping to explore emergence of construction disputes
  publication-title: J. Civ. Eng. Manag.
  doi: 10.3846/jcem.2021.14900
  contributor:
    fullname: Tanriverdi
– volume: 14
  start-page: 05021009
  year: 2022
  ident: ref_10
  article-title: Evaluation of Biases in Construction Project Dispute Resolution: Case Study
  publication-title: J. Leg. Aff. Disput. Resolut. Eng. Constr.
  doi: 10.1061/(ASCE)LA.1943-4170.0000525
  contributor:
    fullname: Tayeh
– volume: 24
  start-page: 261
  year: 2006
  ident: ref_31
  article-title: Risks faced by Singapore firms when undertaking construction projects in India
  publication-title: Int. J. Proj. Manag.
  doi: 10.1016/j.ijproman.2005.11.003
  contributor:
    fullname: Ling
– ident: ref_35
– ident: ref_64
  doi: 10.1007/978-3-030-15009-9
– ident: ref_19
  doi: 10.1007/978-3-319-04429-3
– volume: 148
  start-page: 04021184
  year: 2022
  ident: ref_14
  article-title: Understanding Disputes in Modular Construction Projects: Key Common Causes and Their Associations
  publication-title: J. Constr. Eng. Manag.
  doi: 10.1061/(ASCE)CO.1943-7862.0002208
  contributor:
    fullname: Nabi
– volume: 29
  start-page: 261
  year: 1992
  ident: ref_54
  article-title: On the nature of cognitive maps
  publication-title: J. Manag. Stud.
  doi: 10.1111/j.1467-6486.1992.tb00664.x
  contributor:
    fullname: Eden
– volume: 25
  start-page: 517
  year: 2007
  ident: ref_28
  article-title: Causes and effects of delays in Malaysian construction industry
  publication-title: Int. J. Proj. Manag.
  doi: 10.1016/j.ijproman.2006.11.007
  contributor:
    fullname: Sambasivan
– ident: ref_8
– volume: 26
  start-page: 174
  year: 2008
  ident: ref_43
  article-title: Understanding time delay disputes in construction contracts
  publication-title: Int. J. Proj. Manag.
  doi: 10.1016/j.ijproman.2007.05.002
  contributor:
    fullname: Iyer
– volume: 40
  start-page: 414
  year: 2012
  ident: ref_59
  article-title: An assessment of the use of partial least squares structural equation modeling in marketing research
  publication-title: J. Acad. Mark. Sci.
  doi: 10.1007/s11747-011-0261-6
  contributor:
    fullname: Hair
– volume: 47
  start-page: 161
  year: 2014
  ident: ref_74
  article-title: Rethinking Partial Least Squares Path Modeling: Breaking Chains and Forging Ahead
  publication-title: Long Range Plan.
  doi: 10.1016/j.lrp.2014.02.003
  contributor:
    fullname: Rigdon
– volume: 3
  start-page: 111
  year: 2012
  ident: ref_75
  article-title: A practical guide to calculating Cohen’sf 2, a measure of local effect size, from PROC MIXED
  publication-title: Front. Psychol.
  doi: 10.3389/fpsyg.2012.00111
  contributor:
    fullname: Selya
– ident: ref_60
  doi: 10.1007/978-3-319-71691-6_6
– volume: 4
  start-page: 45
  year: 2012
  ident: ref_20
  article-title: Identification of the relations between dispute factors and dispute categories in construction projects
  publication-title: Int. J. Law Built Environ.
  doi: 10.1108/17561451211211732
  contributor:
    fullname: Ilter
– ident: ref_41
– volume: 34
  start-page: 671
  year: 2003
  ident: ref_25
  article-title: Application of component state model for identifying constructability conflicts in a merged construction schedule
  publication-title: Adv. Eng. Softw.
  doi: 10.1016/S0965-9978(03)00105-4
  contributor:
    fullname: Chua
– ident: ref_1
  doi: 10.1007/978-3-319-04429-3_2
– volume: 15
  start-page: 513
  year: 1997
  ident: ref_33
  article-title: Conflict and dispute in construction
  publication-title: Constr. Manag. Econ.
  doi: 10.1080/014461997372719
  contributor:
    fullname: Fenn
– ident: ref_62
– ident: ref_45
– volume: 20
  start-page: 88
  year: 2004
  ident: ref_4
  article-title: Convergent Views of Neutrals and Users about Alternative Dispute Resolution
  publication-title: J. Manag. Eng.
  doi: 10.1061/(ASCE)0742-597X(2004)20:3(88)
  contributor:
    fullname: Cheung
– volume: 19
  start-page: 139
  year: 2011
  ident: ref_73
  article-title: PLS-SEM: Indeed a silver bullet
  publication-title: J. Mark. Theory Pract.
  doi: 10.2753/MTP1069-6679190202
  contributor:
    fullname: Hair
– volume: 23
  start-page: 480
  year: 2009
  ident: ref_40
  article-title: Divergence or Congruence? A Path Model of Rework for Building and Civil Engineering Projects
  publication-title: J. Perform. Constr. Facil.
  doi: 10.1061/(ASCE)CF.1943-5509.0000054
  contributor:
    fullname: Love
– ident: ref_7
– ident: ref_53
  doi: 10.1007/978-90-481-9097-3_17
– ident: ref_69
  doi: 10.4337/9781781001042.00023
– ident: ref_38
  doi: 10.1007/978-3-030-80256-1_4
– ident: ref_76
– ident: ref_3
– ident: ref_24
– volume: 13
  start-page: 04521031
  year: 2021
  ident: ref_46
  article-title: Sources of Ambiguity in Construction Contract Documents, Reflected by Litigation in Supreme Court Cases
  publication-title: J. Leg. Aff. Disput. Resolut. Eng. Constr.
  doi: 10.1061/(ASCE)LA.1943-4170.0000498
  contributor:
    fullname: Chan
– ident: ref_47
– ident: ref_52
  doi: 10.1007/978-1-84882-809-4
– volume: 42
  start-page: 752
  year: 2007
  ident: ref_27
  article-title: A study of construction mediator tactics—Part I: Taxonomies of dispute sources, mediator tactics and mediation outcomes
  publication-title: Build. Environ.
  doi: 10.1016/j.buildenv.2005.09.004
  contributor:
    fullname: Cheung
– volume: 47
  start-page: 154
  year: 2014
  ident: ref_71
  article-title: On the Emancipation of PLS-SEM: A Commentary on Rigdon (2012)
  publication-title: Long Range Plan.
  doi: 10.1016/j.lrp.2014.02.007
  contributor:
    fullname: Sarstedt
– volume: 14
  start-page: 04521041
  year: 2022
  ident: ref_11
  article-title: Lessons Learned in the Use of Dispute Boards to the Settlement of Construction Service Disputes
  publication-title: J. Leg. Aff. Disput. Resolut. Eng. Constr.
  doi: 10.1061/(ASCE)LA.1943-4170.0000508
  contributor:
    fullname: Fitriyanti
– ident: ref_37
– volume: 24
  start-page: 349
  year: 2006
  ident: ref_29
  article-title: Causes of delay in large construction projects
  publication-title: Int. J. Proj. Manag.
  doi: 10.1016/j.ijproman.2005.11.010
  contributor:
    fullname: Assaf
– volume: 22
  start-page: 218
  year: 2019
  ident: ref_44
  article-title: Causes of disputes, factors affecting dispute resolution and effective alternative dispute resolution for Sri Lankan construction industry
  publication-title: Int. J. Constr. Manag.
  contributor:
    fullname: Illankoon
– ident: ref_21
– volume: 43
  start-page: 589
  year: 2005
  ident: ref_39
  article-title: Dispute resolution management for international construction projects in China
  publication-title: Manag. Decis.
  doi: 10.1108/00251740510593576
  contributor:
    fullname: Chan
– volume: 14
  start-page: 04521046
  year: 2022
  ident: ref_13
  article-title: Investigating the Relationship between Reworks and Contractual Claims: The Salience of Contract Conditions
  publication-title: J. Leg. Aff. Disput. Resolut. Eng. Constr.
  doi: 10.1061/(ASCE)LA.1943-4170.0000519
  contributor:
    fullname: Asadi
– ident: ref_56
  doi: 10.1007/978-3-540-32827-8_3
– ident: ref_67
  doi: 10.4324/9781410604385
– ident: ref_57
  doi: 10.1007/978-3-319-71691-6
– volume: 40
  start-page: 434
  year: 2012
  ident: ref_68
  article-title: Guidelines for choosing between multi-item and single-item scales for construct measurement: A predictive validity perspective
  publication-title: J. Acad. Mark. Sci.
  doi: 10.1007/s11747-011-0300-3
  contributor:
    fullname: Diamantopoulos
– volume: 8
  start-page: 45641
  year: 2020
  ident: ref_2
  article-title: Methods for Modeling and Evaluating Construction Disputes: A Critical Review
  publication-title: IEEE Access
  doi: 10.1109/ACCESS.2020.2976109
  contributor:
    fullname: Naji
– volume: 19
  start-page: 1
  year: 1991
  ident: ref_78
  article-title: Multivariate adaptive regression splines
  publication-title: Ann. Stat.
  contributor:
    fullname: Friedman
– ident: ref_50
– volume: 17
  start-page: 404
  year: 2010
  ident: ref_5
  article-title: Dispute causation: Identification of pathogenic influences in construction
  publication-title: Eng. Constr. Arch. Manag.
  doi: 10.1108/09699981011056592
  contributor:
    fullname: Love
– volume: 29
  start-page: 453
  year: 2021
  ident: ref_17
  article-title: Two-layered fuzzy logic-based model for predicting court decisions in construction contract disputes
  publication-title: Artif. Intell. Law
  doi: 10.1007/s10506-021-09281-9
  contributor:
    fullname: Ravanshadnia
– volume: 128
  start-page: 18
  year: 2002
  ident: ref_6
  article-title: Influence of Project Type and Procurement Method on Rework Costs in Building Construction Projects
  publication-title: J. Constr. Eng. Manag.
  doi: 10.1061/(ASCE)0733-9364(2002)128:1(18)
  contributor:
    fullname: Love
– ident: ref_61
  doi: 10.1007/978-3-540-32827-8_15
– volume: 2018
  start-page: 3696457
  year: 2018
  ident: ref_65
  article-title: DEMATEL technique: A systematic review of the state-of-the-art literature on methodologies and applications
  publication-title: Math. Probl. Eng.
  doi: 10.1155/2018/3696457
  contributor:
    fullname: Si
– volume: 14
  start-page: 04521049
  year: 2022
  ident: ref_12
  article-title: Framework for the Successful Implementation of Dispute Boards in Construction Projects
  publication-title: J. Leg. Aff. Disput. Resolut. Eng. Constr.
  doi: 10.1061/(ASCE)LA.1943-4170.0000520
  contributor:
    fullname: Waly
– ident: ref_66
  doi: 10.1007/978-3-030-80519-7
– volume: 1
  start-page: 117
  year: 2001
  ident: ref_23
  article-title: A fuzzy sets model for construction dispute evaluation
  publication-title: Constr. Innov.
  doi: 10.1108/14714170110814550
  contributor:
    fullname: Cheung
– ident: ref_36
– volume: 139
  start-page: 15
  year: 2013
  ident: ref_77
  article-title: Anatomy of Construction Disputes
  publication-title: J. Constr. Eng. Manag.
  doi: 10.1061/(ASCE)CO.1943-7862.0000532
  contributor:
    fullname: Cheung
– ident: ref_34
  doi: 10.1007/978-1-349-21005-3_20
– ident: ref_42
  doi: 10.1061/9780784402764
– ident: ref_72
  doi: 10.1108/S1474-7979(2009)0000020014
SSID ssj0000852254
Score 2.2688808
Snippet Project claim management is the central pillar of the overlapping areas of contract administration, contract law and building regulations. Delays caused by...
SourceID doaj
proquest
crossref
SourceType Open Website
Aggregation Database
StartPage 1571
SubjectTerms Bias
Causal Analysis
construction
Construction industry
Contract administration
Contract law
Costs
dispute
Forensic Analysis
Forensic science
Jurisdiction
Mathematical models
PLS-SEM
Project engineering
Project management
Quantitative analysis
Questionnaires
Trend Analysis
Typology
Title Forensic Analysis of the Disputes Typology of the NSW Construction Industry Using PLS-SEM and Prospective Trend Analysis
URI https://www.proquest.com/docview/2728448449
https://doaj.org/article/403478c3ca4947799f390b952120a7af
Volume 12
hasFullText 1
inHoldings 1
isFullTextHit
isPrint
link http://sdu.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwrV07T8MwELaACQbEU5SXPDAhRXVip7ZHoEUdoKpUEGyRX5FgSBEBCf49d05SFXVgQcrkxEn0nX32JXffR8jFwBlYNHiZOJ5miRCGJRrV3A04Qmgy0ngsTh7P5ORZDUdIk7OQ-sKcsIYeuAGuLxgXUjnujNBCSq1LiNKtxpJTBncqo_dlaimYem2yr2CgiuY3JocefduqTNfImJXmMv21EEW-_hV3HNeY2x2y3W4O6VXzUrtkLVR7ZGuJMnCffKGWZgXQ0o5OhM5LCrs4OnypUZ-hphBaxm_l3YnJ7ImiLmfHFEtbuY5vGvMF6PRuBl71nprK0-n7vKu9pDFddvGYA_J4O3q4GSetegLArrKPxHkXACWvvMlzFZx0diBSz0sdOGbnlcwKJ5nJSzBQgG2QCsJnzA2gJXiT8UOyUc2rcIR13TozOfOpcFoIaw3M-gCxj4WeylnfI5cdlMVbQ5JRQHCBuBcruPfINYK9uBD5rWMDWL1orV78ZfUeOe1MVbSTri4yCWutgEMf_8czTshmhrUOMXPvlGyAlcIZWa_953kcbD9tstob
link.rule.ids 315,782,786,866,2108,27935,27936
linkProvider Directory of Open Access Journals
openUrl ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Ajournal&rft.genre=article&rft.atitle=Forensic+Analysis+of+the+Disputes+Typology+of+the+NSW+Construction+Industry+Using+PLS-SEM+and+Prospective+Trend+Analysis&rft.jtitle=Buildings+%28Basel%29&rft.au=Rahnamayiezekavat%2C+Payam&rft.au=Sorooshnia%2C+Ehsan&rft.au=Rashidi%2C+Maria&rft.au=Faraji%2C+Amir&rft.date=2022-10-01&rft.pub=MDPI+AG&rft.eissn=2075-5309&rft.volume=12&rft.issue=10&rft.spage=1571&rft_id=info:doi/10.3390%2Fbuildings12101571&rft.externalDBID=HAS_PDF_LINK
thumbnail_l http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/lc.gif&issn=2075-5309&client=summon
thumbnail_m http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/mc.gif&issn=2075-5309&client=summon
thumbnail_s http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/sc.gif&issn=2075-5309&client=summon